A federal judge ordered 48 hours' notice before any ground activity at the site of the planned 250-foot veterans arch near Arlington National Cemetery, as Interior Secretary Doug Burgum prepares to begin excavation within weeks.
A federal judge has ordered the Trump administration to provide 48 hours' notice before any ground activity at the site of the planned 250-foot veterans arch near Arlington National Cemetery. The ruling keeps the project on track while adding a procedural step, one day after Interior Secretary Doug Burgum announced excavation work could begin within weeks.
U.S. District Judge Tanya Chutkan issued the order Friday in response to an emergency filing from a group of three military veterans and an architectural historian seeking to block the project. The judge did not halt the project outright, instead requiring the government to inform the court before engaging in any activity on Memorial Circle other than on-site information gathering to identify underground cultural artifacts.
Burgum announced Thursday that the department is preparing to start excavation work for the Great Triumphal Arch and Military Observation Deck at Memorial Circle on Columbia Island, located between the Lincoln Memorial and Arlington National Cemetery. He described the project as one of the great pieces of American architecture, honoring the history of Arlington Cemetery.
According to a government court filing, the planned activity involves mechanically excavating four test pits no earlier than September 21, with the land expected to be restored by October 31. Administration lawyers said the work is standard archaeological survey activity, not construction or demolition in preparation for construction.
The opponents, who filed suit in February, argue the administration has no legal basis for construction work and that the arch violates federal law and requires approval from Congress. They asked Chutkan on Friday for a 14-day restraining order to block any steps to construct or direct construction of a structure in Memorial Circle.
The government contends a 1925 law that authorized the now-defunct commission behind Washington's Arlington Memorial Bridge provides congressional approval for the arch. The opponents dispute that reading, and the project also awaits final approval from the National Capital Planning Commission, which must decide whether to grant an exception to the 130-foot building height limit that applies to most of the capital.
Chutkan's latest order reinforces restrictions she first put in place this spring, when she questioned the administration's authority to build the arch and the government agreed to provide 14 days' notice before starting construction under a consent order. Friday's ruling tightens that arrangement by requiring 48 hours' notice to the court before any site activity beyond archaeological information gathering.
Chutkan also reiterated that any construction or demolition in preparation for construction before the National Park Service issues final authorization, or without providing 14 days' notice, would violate her orders.
The arch is one of several projects the administration has pursued to reshape the nation's capital, joining a new White House ballroom, renovation of the Lincoln Memorial Reflecting Pool, and redevelopment of a golf course in East Potomac Park. The design, which evokes Paris' Arc de Triomphe, would rise near the sprawling military burial ground that supporters say the monument would honor.
Opponents claim the arch would disrupt the cemetery's historic sight line between the Lincoln Memorial and Arlington House across the Potomac. They pointed to the White House ballroom as a cautionary tale, noting the Supreme Court last week allowed that construction to continue in a 5-4 ruling while legal challenges proceed.
For now, the arch project moves forward. Interior plans to begin the archaeological test-pit work later this month, and the coming weeks will determine whether the legal fight delays the groundbreaking or clears the way for construction.